Key takeaways
- Most Odoo project problems start with decisions and documents, not software.
- On the TAM Trading project, we recorded 25 open decisions in the Finance specification instead of guessing them.
- Hard rules need worked examples, and the scope needs a clear out-of-scope list.
- Odoo 19 changed some behaviour that trading companies rely on. Test critical controls in the exact version before promising them [1][2].
- Data, training and testing are where good plans slip. Start them earlier than feels necessary.
Overview
This article lists the mistakes we plan for on our own projects, with examples from the requirements we wrote for TAM Trading, a GCC chemical trader running three entities in one Odoo database. For each mistake, we say what we do about it.
| Mistake | What we do |
|---|---|
| 1. Guessing undecided policies | Keep an open decision list with owners |
| 2. Rules without examples | Add a worked example to every hard rule |
| 3. Unwritten scope boundaries | Write an out-of-scope section per area |
| 4. Treating scope changes as failure | Agree a change request process up front |
| 5. Assuming features work the same in every version | Test critical controls in the exact version |
| 6. Finding out about licensing late | Confirm the Odoo plan early |
| 7. Underestimating client inputs | Request documents early and track them weekly |
| 8. Migrating dirty data | Clean data in parallel with the build |
| 9. Customising before trying standard | Try standard and configuration first |
| 10. Training only at the end | Name key users early and involve them in testing |
| 11. Testing features, not business scenarios | Test full deals from enquiry to payment |
| 12. Going live without a readiness check | Hold a go or no-go review with clear criteria |
1. Guessing policies the client has not decided
During requirements, some questions have no answer yet. In TAM’s Finance specification, 25 questions were still open, for example:
- How often to recover input VAT for the Free Zone entity
- Whether late-payment interest charged by a service provider is passed on
- How long payments can be held during a dispute, and the rules for partial payments
- How to estimate and allocate lower-leg costs to inventory or cost of goods sold
If the partner guesses, the system enforces a rule nobody agreed to. What we do: keep open decisions on a separate list, each with an owner, and do not configure them until they are answered. This is why how we plan an implementation starts with a list of open items.

2. Writing rules without examples
“Deals above 500 MT need approval” sounds clear until someone asks whether it applies to a split proforma. We write a worked example next to each hard rule. TAM’s approval rule, for instance, includes a 600 MT soda ash example that walks through exactly what the system blocks and who must approve. In a packaging project, worked examples exposed several conflicts between departments.
3. Leaving scope boundaries unwritten
Every TAM specification has an out-of-scope section. The Sales specification states that RFQ data is entered manually, with no automatic extraction from documents. The Finance specification excludes treasury management and bank API integration. Writing these down early prevents disappointment at testing.
4. Treating scope changes as failure
Scope grows when teams see the first version. Between 5 and 23 December 2025, TAM’s Supply Chain team added 13 requirements, including vendor validation, document expiry alerts, MSDS version control and consignee stock.
What we do: agree at the start that new requirements after sign-off go into a later phase, estimated separately through a change request.
5. Assuming a feature works the same in every Odoo version
Two Odoo 19 behaviours matter for traders:
- Credit limits. Odoo 19 removed the Warning / Block choice on customer warnings. Users can still confirm an order when the customer is over the limit [1].
- Landed costs after a sale. With AVCO and perpetual valuation, a landed cost validated after part of the stock is sold may only revalue the remaining stock [2].
TAM’s design depends on hard blocks and accurate landed cost, so both needed a planned solution, not an assumption. What we do: list the controls the business depends on, and test each one in the exact Odoo version before it goes into the design.
6. Finding out about licensing late
TAM runs three entities in one database. On Odoo’s pricing, multi-company, Studio and custom modules all require the Custom plan [3]. If this comes up late, the budget changes after it has been approved. What we do: confirm the plan early, based on entities, customisation and hosting. We explain the licence side in what drives Odoo cost.
7. Underestimating how long client inputs take
On our projects, the most common reasons for delay are on both sides: documents and calculations the client has not yet provided, key people unavailable for review meetings, and requirements that change after approval. Technical issues and team availability play a part too. Data held by outside partners is a common cause; see data held by partners.
What we do: share templates and document requests early, book review meetings in advance, and track pending client inputs in the weekly progress report.
8. Migrating dirty data
Duplicate customers, products with three different names, and opening stock nobody has counted all end up in the new system if nobody cleans them. Data work is often left until the last weeks because it feels like admin.
What we do: share import templates early, name an owner for each data set, and run at least one trial import before go-live. Opening stock and balances are confirmed by the client, not assumed.
A typical example from trading: opening stock imported from the last spreadsheet, without a fresh count. The first deliveries then fail because the system thinks stock is in a location where it is not. On TAM, the requirements assume TAM provides clean master data and a physical count for opening stock.
9. Customising before trying standard
Every custom feature has to be maintained and carried through future upgrades. Teams sometimes ask for development because a screen looks different from what they are used to, not because the standard process cannot work.
What we do: try each requirement in standard Odoo first, then configuration, and only then development. On a packaging project, the plan came out at about 60% standard, 30% configuration and 10% development.
If your team is planning an Odoo project and wants to avoid these mistakes, we can review your requirements before you commit.
10. Training only at the end
When training happens in the last two weeks, users see the system for the first time just before they must use it. Questions that should have shaped the design arrive too late.
What we do: name key users in each department at the start, involve them in reviews and testing, and have them help train their colleagues. User manuals are written per role.
11. Testing features, not business scenarios
Testing that each screen works is not the same as testing that the business works. A sales order can be correct and still produce the wrong landed cost or block the wrong supplier PO.
What we do: test full scenarios with real examples, such as one deal from enquiry through LC, shipment, delivery and payment, with the people who will run it.
12. Going live without a readiness check
Go-live dates are often fixed early and treated as promises. If master data, training or a key control is not ready, going live anyway moves the problem into daily operations.
What we do: hold a go or no-go review a week before go-live, with clear criteria: data verified, key scenarios passed, users trained, cut-over plan agreed and support in place.

Warning signs a project is going off track
- Open decisions have no owner or no date.
- The same requirement is discussed in three meetings without being closed.
- Data templates were shared but nothing has come back.
- Key users miss review meetings or send someone else.
- Testing finds problems in requirements, not just in configuration.
- The go-live date is discussed more than the readiness criteria.
Any one of these is normal for a week. Two or more for a month means the plan needs a reset, not more effort.
Checklist before you sign off requirements
- Every requirement has an ID, a priority and a status.
- Hard rules have worked examples.
- Out-of-scope items are written down.
- Open decisions are on a separate list, each with an owner.
- Critical controls have been tested in the exact Odoo version.
- The Odoo plan is confirmed.
- You know how changes after sign-off will be handled.
- Data owners and key users are named.
FAQ
What usually makes an Odoo project run late?
In our experience: pending client documents and decisions, unavailable reviewers and changing requirements, plus some technical issues.
Should we expect scope changes?
Yes. On TAM, 13 Supply Chain requirements were added during review. Plan for it.
Do Odoo features change between versions?
Yes. Credit warnings and landed cost behaviour both changed in Odoo 19 [1][2].
How much should be custom development?
As little as the business needs. Try standard Odoo and configuration first, because every custom feature has to be maintained through upgrades.
When should training start?
Earlier than most plans allow. Key users should be involved from the design reviews, not only in the final weeks.
Plan for the problems before they start
If you are preparing an Odoo project, start with the list of decisions your team has not made yet. We can help you build it. Read more about our Odoo implementation service.
References
[1] Odoo Community Forum, Sale Warning on Contacts [V19]. https://www.odoo.com/forum/help-1/sale-warning-on-contacts-v19-295615
[2] Odoo Community Forum, Landed Cost Impact on COGS (Odoo v19 observation). https://www.odoo.com/forum/help-1/landed-cost-impact-on-cogs-odoo-v19-observation-297080
[3] Odoo, Pricing. https://www.odoo.com/pricing